Construction Status Update for January / February 2015

Feb 28 2015

It has been another very busy and exciting two months at the Eagle Creek Village site as it’s really starting to take shape. Buildings 2 and 6’s parkades are nearing completion with 93% of the slab on grade and 89% of the suspended slaps complete to date. The Building 7 stair/elevator core walls have been poured up to level 2 and Buildings 3 and 4 stair/elevator core walls have been prepped and are ready to be poured. For Building 8, steel stud interior wall framing and roofing is underway. While over at Building 6 structural steel is ready to begin. The earthworks contractor continues with excavating and backfilling for concrete foundations and installation of underground services.

Major Milestones:
• Completion of 95% of bulk blasting work (including CCN and CD work).
• Concrete work began January, 30 2015.
• Building Permits for Buildings 2, 3 and 4 have been received.