Construction Status Update for July / August 2015

Aug 28 2015

Eagle Creek Village's progress over the summer has been excellent. All of the buildings have steel structure completed and the shopping centre is taking form. Concrete and reinforcing work was completed in Buildings 1, 3, 4 and 5 areas, meanwhile Building 7 structural steel and decking is complete and the concrete toppings have been poured. Structural steel for buildings 2 and 5 have also completed. The earthworks contractor continued with excavation and installation of underground utilities both on and off site. Mechanical and electrical contractors continued performing work related to underground and in slab services, as well as rough in for the parkade and buildings 2, 5, 6, 7 and 8 rough in and steel stud wall framing and roofing continued for buildings 2, 5, 7 and 8.

Upcoming Major Milestones:

  • Building 2: Continue electrical and mechanical rough in and exterior envelope work. 
  • Building 3 and 4: Complete framing including roof for building 3 (residential rental).
  • Building 5: Complete framing and start exterior envelope work.
  • Building 8: Handover for tenant improvements.