Construction Status Update for March / April 2015

May 1 2015

March and April have been incredibly productive at the Eagle Creek Village site. Buildings 2 and 6’s parkades are nearing completion with 95% of the slab on grade and 93% of the suspended slaps complete to date. The Building 7 stair / elevator core walls have been completed with steel erection scheduled to begin shortly. Steel stud wall framing and roofing is underway for building 6. Structural steel for building 6 is approximately 90% complete. Building 2 structural steel is now underway. The earthworks contractor continues with excavating and backfilling for concrete foundations and installation of underground services in buildings 3 and 4 and remaining parkade area.

Upcoming Major Milestones:
• Complete remaining parkade walls.
• Complete erection of building 6 structural steel.
• Complete erecting structural steel for building 2.