Construction Status Update for May / June 2015

Jun 30 2015

May and June were tremendously productive at Eagle Creek Village. The project is beginning to take shape, with most of the building’s steel structure established and siding either underway or completed.  Building 7's structural steel is nearly complete and concrete toppings are being poured. The earthworks contractor is continuing with excavating and backfilling for concrete foundations and installation of underground services in building 3, 4 and 5 areas. Mechanical and electrical contractors have continued performing work related to underground and in-slab services, as well as rough-in for the parkade and buildings 2, 6, 7 and 8 rough-in. Steel stud wall framing and roofing is underway for buildings 2, 5 and 8.

Upcoming Major Milestones:
• Complete steel decking for the office building and associated concrete toppings. Continue framing exterior steel stud walls and begin glass installation.
• Complete pouring of suspended slabs for buildings 3 and 4 and continue wood framing.
• Complete steel stud framing for building 2 and begin glass installation.